At the March 20 meeting of the Memphis-Shelby County Airport Authority (MSCAA) Board of Commissioners meeting, design consultants UrbanArch and Alliiance provided an update on Memphis International Airport’s Terminal Modernization and Seismic Program (TMSP).

The update included a presentation with updated conceptual renderings and fly-through videos. This portion of the project is expected to begin in 2027.

Following is a recap of the estimated project timeline:

  • Creation of an additional commercial lane on the baggage level: Ongoing
  • Relocation of ride-share services to new commercial lane: Spring/Summer 2025 (upon completion of commercial lane project)
  • Outer drive replacement: Starting Summer 2025
  • Terminal Building Modernization: Starting 2027