At the March 20 meeting of the Memphis-Shelby County Airport Authority (MSCAA) Board of Commissioners meeting, design consultants UrbanArch and Alliiance provided an update on Memphis International Airport’s Terminal Modernization and Seismic Program (TMSP).
The update included a presentation with updated conceptual renderings and fly-through videos. This portion of the project is expected to begin in 2027.
Following is a recap of the estimated project timeline:
- Creation of an additional commercial lane on the baggage level: Ongoing
- Relocation of ride-share services to new commercial lane: Spring/Summer 2025 (upon completion of commercial lane project)
- Outer drive replacement: Starting Summer 2025
- Terminal Building Modernization: Starting 2027
The new renderings as well as a recap of this and other improvement projects can be found at https://flymemphis.com/mem-on-the-move/.